Ringhals Nuclear Power Plants (Sweden): Electrochlorination Package
Successful Commissioning & Start-up of the Electrochlorination Package installed at Ringhals Nuclear Power Plants 2×1000 MW rated capacity.
As per Contact, on Turn Key Basis, awarded to our Company by VATTENFALL Group on 2013, IDRECO has supplied the Electrochlorination Package composed by N° 2 trains each one with a capacity of 50 kg/h as produced Cl2 from Sea Water.
Designing, manufacturing, delivering, erection and putting in service of the Package has been accomplished in 16 months form Contract awarding date.
Eurotecnica (Italy): Melamine Steam Tube Dryer for Chinese Facility in Xinjong Zhundong
Successful delivery of N° 1 Melamine Steam Tube Dryer for Xinjong Zhundong Chinese Facility.
As per Contact awarded to our Company by EUROTECNICA on 2015, IDRECO has supplied N° 1 Steam Tube Dryer to be installed in a new Melamine Facility.
Supplied Steam Tube Dryer has a capacity of 60.000 metric ton/year of Melamine.
Delivery of the Packages has been accomplished in 8 months form Contract awarding date.
This achievement confirms once more IDRECO as worldwide leading Company in the design and manufacturing of Steam Tube Dryers, mainly in Melamine production process.