Birla Group Trecate (Italy): Carbon Black Dryers
Successful execution of the Commissioning & Start-up of the supplied Carbon Black Dryer installed in the production line N° 3 as scheduled.
As far as today, all the five Carbon Black production lines of the Trecate site are equipped with IDRECO Dryers as confirmation about the reliability of the IDRECO equipment and about IDRECO as worldwide leading Company in the design and manufacturing of Carbon Black Dryers
Besmaya Thermal Power Plant phase 2 (Iraq): Condensate Filtration Packages
Our Company has been awarded by Greek EPC Contractor J&P AVAX International Ltd. of the Contract for the supply of No. 2 Condensate Filtration Packages.
Each of the 2 Packages is equipped with 2 Filters each one design to treat 1130 m3/h of Raw Condensate.
Each of the 4 filters is equipped with high performance backwashable cartridge filtering elements.
Columbian Carbon Europa srl (Italy): Carbon Black Dryers
Successful execution of the Commissioning & Start-up of the supplied Carbon Black Dryer installed in the production line N° 2.
On June 2017, Our Company has been awarded by COLUMBIAN CARBON EUROPA srl of the Contract for the supply of No. 2 Carbon Black Dryers (capacity of 70 ton/day each one) to replace the existing old dryers, manufactured by other, on production lines 2 and 3.
Delivery of the 2 Dryers has been accomplished in 6 months form Contract awarding date.
Start up & Commissioning of new dryer to be installed in production line N° 3 is scheduled for next July 2018.
By July 2018, all the 5 lines of Carbon Black production of the Columbian Carbon Europa Facility will be equipped with Dryers manufactured by IDRECO.
This achievement confirms once more IDRECO as worldwide leading Company in the design and manufacturing of Carbon Black Dryers.
ONT – Office National de la Télédiffusion (Tunisia): Carbon Black Dryers
IDRECO ha been awarded by Client with the Contract for the supply of engineering, procurement, installation of level controller for BF signals with bargraph display display (audio monitoring with bargraph display.
Equipment and devices included in the Contract are part of the first DAB system in Africa.
Ringhals Nuclear Power Plant (Sweden): Ion Exchange Resins Supply
Renewal for a period of 3 years of the Agreement for the supply of the ion exchange resins to Ringhals Nuclear Power Plant in Sweden.
This new agreement strength the over 30 years relationship between IDRECO and VATTENFALL group.
Eurotecnica (Italy): Melamine Steam Tube Dryer for Chinese Facility in Xinjiang
Successful delivery of N° 1 Melamine Steam Tube Dryer for Xinjiang Chinese Facility.
As per Contact awarded to our Company by EUROTECNICA on 2017, IDRECO has supplied N° 1 Steam Tube Dryer to be installed in the new Melamine Facility.
Supplied Steam Tube Dryer has a capacity of 60.000 metric ton/year of Melamine.
Delivery of the Packages has been accomplished in 8 months form Contract awarding date.
This achievement confirms once more IDRECO as worldwide leading Company in the design and manufacturing of Steam Tube Dryers, mainly in Melamine production process.
KIMA Ammonia & Urea Fertilizer Project in Aswan (Egypt): Water Treatment Packages
Successful delivery of the Water Treatment Packages to KIMA Ammonia & Urea Fertilizer Project.
As per Contact awarded to our Company by TECNIMONT on 2016, IDRECO has supplied the following Water Treatment Packages:
• Pretreatment Water Package (Clariflocculation, Filtration, Sludge Dewatering Sections and auxiliary systems) having capacity of 1.000 m3/h of treated water
• Demineralization Package (Activated Carbon Filters, Cation Ion Exchanger, Forced Draft Decarbonator, Anion Ion Exchanger and auxiliary systems) composed by 2 trains each one having capacity of 240 m3/h of produced demineralized Water.
• Polishing Package (Mixed Bed Ion Exchangers and auxiliary systems) composed by 2 trains each one having capacity of 440 m3/h of produced Polished Condensate.
• Side Stream Filtering Package composed by N° 2 Gravity Sand Filters for Cooling Tower Water Filtration each one having capacity of 685 m3/h for a total flow of 1.370 m3/h of Filtered Water
Delivery of the Packages has been accomplished in 12 months form Contract awarding date.
West Damietta & Al Shabab Thermal Power Plants (Egypt): Condensate Filtration Packages
Successful delivery of the Condensate Polishing Filtration Systems to West Damietta and Al Shabab Thermal Power Plants.
As per Contact awarded to our Company by TECHINT on 2016, IDRECO has supplied N° 2 Condensate Polishing Filtration Packages to Al Shabab Power Plant (one for each 750 MW Power Unit) and N° 1 Condensate Polishing Filtration Package to West Damietta Power Plant (for the 750 MW Power Unit).
Each of the 3 Condensate Polishing Filtration Packages has a capacity of 640 m3/h of Treated Condensate.
Delivery of the Packages has been accomplished in 6 months form Contract awarding date.
Baja California Unit 3 Thermal Power Plants (Mexico): Electrochlorination Package
Successful Commissioning & Start-up of the Electrochlorination Package installed at Baja California Unit 3 Thermal Power Plant 1×300 MW rated capacity.
As per Contact, on Turn Key Basis, awarded to our Company by IBERDROLA on 2015, IDRECO has supplied the Electrochlorination Package composed by N° 2 trains each one with a capacity of 35 kg/h as produced Cl2 from Sea Water.
Designing, manufacturing, delivering, erection and putting in service of the Package has been accomplished in 18 months form Contract awarding date.
Planta Monsayer Tlalnepantla (Mexico): Industrial Liquid & Gases Wastes Incinerator System
Successful Commissioning & Start-up of N° 1 Industrial Liquid & Gases Waste Incinerator System.
As per Contact awarded to our Company by SAYER LACK MEXICANCA on 2013, IDRECO has supplied N° 1 Industrial Incinerator System for Liquid & Gases Wastes.
Supplied Incinerator System has a capacity of 525 kg/h of Industrial Liquid Wastes and Exhaust Solvents as well as Xylene.
The system is composed by the following main sections:
• Combustion chamber
• Liquid waste burner
• Xylene pumping station and burner
• Heat recovery from flue gas for thermal oil used in the factory and for combustion air
• Self supporting stack with Exhauster Air Fan
Delivery of the Packages has been accomplished in 9 months form Contract awarding date.